Mindanao Container Terminal (MCT), International Container Terminal Services, Inc.'s (ICTSI) operation in the Philippines supporting Northern Mindanao trade, is ramping up capacity to accommodate rising cargo demand and additional shipping services.
The arrival of four hybrid rubber-tired gantry (RTG) cranes marks the latest step in an expansion program that includes a 300-metre berth extension, orders of three post-Panamax quay cranes, expanded reefer facilities, and additional container storage capacity.
"We formalised the project in late 2024 and established a clear timetable. I'm pleased to say that everything remains on schedule," said Aurelio C. Garcia, MCT Chief Executive Officer. "The RTGs arrived roughly three months ahead of schedule, marking an important step in the terminal's expansion."
Construction of the berth extension is progressing, with the first 120 metres targeted for completion by the end of the first quarter of 2027. The first of three new post-Panamax quay cranes is expected to arrive shortly afterward and will become operational following commissioning. Once completed, the initial phase will increase MCT's operational berth length to 420 metres, providing additional capacity for vessel calls and shipping services.
The expansion also includes additional infrastructure to support MCT's growing operations. MCT is expanding its reefer facilities to accommodate increasing volumes of refrigerated import and export cargo, while work is underway to expand the empty container depot and increase container storage capacity.
Supporting infrastructure projects include the construction of a new electrical substation that will provide the power required for additional equipment and future operational needs.
Located within the Phividec Industrial Estate, MCT serves as Northern Mindanao's primary international container gateway. The terminal supports the movement of import and export cargoes and helps connect businesses across the region with domestic and international markets.
The current phase forms part of MCT's long-term expansion program, which is scheduled for completion in the first quarter of 2028. By then, MCT is expected to complete the full 300-metre berth extension and commission all three quay cranes. "